Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2020-02-18 13:56 Permalink open Rev 8 and make rev 7 a open Rev 8 and make rev 7 a baseline then select maintain baselines and select update then from here you can choose what to update all activities or a filter or additional update options under Update options pick and choose what to update when you are done select Restore to put REV7 back into the selectable projects Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-02-18 09:42 Permalink Hello Mike,I would rather Hello Mike, I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6 Alexandre Member for 14 years 9 months Member for 14 years 9 months Submitted by plannertheworld on Tue, 2020-02-18 09:13 Permalink Hmnn... not that easy, Hmnn... not that easy, because i have changed some duration and logic. I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another Many thanks Mike Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2020-02-17 23:15 Permalink Don't you just make a copy of Don't you just make a copy of Rev 08 and then delete the new activities? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2020-02-18 13:56 Permalink open Rev 8 and make rev 7 a open Rev 8 and make rev 7 a baseline then select maintain baselines and select update then from here you can choose what to update all activities or a filter or additional update options under Update options pick and choose what to update when you are done select Restore to put REV7 back into the selectable projects
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Tue, 2020-02-18 09:42 Permalink Hello Mike,I would rather Hello Mike, I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6 Alexandre
Member for 14 years 9 months Member for 14 years 9 months Submitted by plannertheworld on Tue, 2020-02-18 09:13 Permalink Hmnn... not that easy, Hmnn... not that easy, because i have changed some duration and logic. I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another Many thanks Mike
Member for 20 years 6 months Member for 20 years 6 months Submitted by Santosh Bhat on Mon, 2020-02-17 23:15 Permalink Don't you just make a copy of Don't you just make a copy of Rev 08 and then delete the new activities?
Member for
16 years 3 monthsopen Rev 8 and make rev 7 a
open Rev 8 and make rev 7 a baseline
then select maintain baselines and select update
then from here you can choose what to update all activities or a filter or additional update options under Update options
pick and choose what to update
when you are done select Restore to put REV7 back into the selectable projects
Member for
22 years 9 monthsHello Mike,I would rather
Hello Mike,
I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6
Alexandre
Member for
14 years 9 monthsHmnn... not that easy,
Hmnn... not that easy, because i have changed some duration and logic.
I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another
Many thanks
Mike
Member for
20 years 6 monthsDon't you just make a copy of
Don't you just make a copy of Rev 08 and then delete the new activities?