Doubt P6 - At Complete versus BL Project

Member for

16 years 3 months

then get access to it or talk to the adminstrative person who does have rigths to this

Member for

15 years 11 months

Suggests to Set the Planned Dates equal to Current Dates.

Member for

6 years 2 months

Hello Zoltan, 

 

I don't have access to Admin menu 

 

Is there another solution to this problem?  Regards,

Member for

6 years 2 months

Hello Zoltan, 

I don't have access to Admin menu
 
Is there another solution to this problem?
 
 
Regards,

Member for

16 years 3 months

go to

Admin 

Admin Preferences

go to the Earned Value tab 

at the bottom where it says Earned Value Calculation When calculating value form a baseline use

change this to Budgeted value with current dates or At completion values with current dates