Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-09-05 13:36 Permalink then get access to it or talk then get access to it or talk to the adminstrative person who does have rigths to this Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2019-09-05 06:37 Permalink Suggests to Set the Planned Suggests to Set the Planned Dates equal to Current Dates. Member for 6 years 2 months Member for 6 years 2 months Submitted by thundermaster on Wed, 2019-09-04 20:12 Permalink Hello Zoltan, I don't have Hello Zoltan, I don't have access to Admin menu Is there another solution to this problem? Regards, Member for 6 years 2 months Member for 6 years 2 months Submitted by thundermaster on Wed, 2019-09-04 20:08 Permalink Hello Zoltan, I don't have Hello Zoltan, I don't have access to Admin menu Is there another solution to this problem? Regards, Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2019-09-04 13:41 Permalink go toAdmin Admin go to Admin Admin Preferences go to the Earned Value tab at the bottom where it says Earned Value Calculation When calculating value form a baseline use change this to Budgeted value with current dates or At completion values with current dates Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-09-05 13:36 Permalink then get access to it or talk then get access to it or talk to the adminstrative person who does have rigths to this
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2019-09-05 06:37 Permalink Suggests to Set the Planned Suggests to Set the Planned Dates equal to Current Dates.
Member for 6 years 2 months Member for 6 years 2 months Submitted by thundermaster on Wed, 2019-09-04 20:12 Permalink Hello Zoltan, I don't have Hello Zoltan, I don't have access to Admin menu Is there another solution to this problem? Regards,
Member for 6 years 2 months Member for 6 years 2 months Submitted by thundermaster on Wed, 2019-09-04 20:08 Permalink Hello Zoltan, I don't have Hello Zoltan, I don't have access to Admin menu Is there another solution to this problem? Regards,
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2019-09-04 13:41 Permalink go toAdmin Admin go to Admin Admin Preferences go to the Earned Value tab at the bottom where it says Earned Value Calculation When calculating value form a baseline use change this to Budgeted value with current dates or At completion values with current dates
Member for
16 years 3 monthsthen get access to it or talk
then get access to it or talk to the adminstrative person who does have rigths to this
Member for
15 years 11 monthsSuggests to Set the Planned
Suggests to Set the Planned Dates equal to Current Dates.
Member for
6 years 2 monthsHello Zoltan, I don't have
Hello Zoltan,
I don't have access to Admin menu
Is there another solution to this problem? Regards,
Member for
6 years 2 monthsHello Zoltan, I don't have
Hello Zoltan,
Member for
16 years 3 monthsgo toAdmin Admin
go to
Admin
Admin Preferences
go to the Earned Value tab
at the bottom where it says Earned Value Calculation When calculating value form a baseline use
change this to Budgeted value with current dates or At completion values with current dates