at the project level make sure that you project is open and highlighted
on the calculations tab make sure that on the right under resource assignments that when updating actual units or costs that Subtract Actual from at completion is checked
make sure that re-calculate actual units and cost when duration % complete changes
make sure that Link actual and actual this period units and costs is checked
The problem here is that you are using physical % complete and updating actuals is based on duration % complete
you have 3 options
option #1 change the % complete type to Duration
option #2 run a global change
where Physical % complete is not equal to 0
then Duration % Complete = Physical % complete
Then on the right select Change
Then in the lower right select Commit Changes
option #3 update them manually as you are doing now
Member for
16 years 3 monthsyeah I think I said that but
yeah I think I said that but there is mote to that than just that other setting to adjust
Member for
17 years 4 monthsHi David,try updating the
Hi David,
try updating the duration percent, it will drive the actual untis to change automatically.
If the setting is physical percent, always you have to manually input the actual values.
BR
Kannan
Member for
16 years 3 monthsat the project level make
at the project level make sure that you project is open and highlighted
on the calculations tab make sure that on the right under resource assignments that when updating actual units or costs that Subtract Actual from at completion is checked
make sure that re-calculate actual units and cost when duration % complete changes
make sure that Link actual and actual this period units and costs is checked
The problem here is that you are using physical % complete and updating actuals is based on duration % complete
you have 3 options
option #1 change the % complete type to Duration
option #2 run a global change
where Physical % complete is not equal to 0
then Duration % Complete = Physical % complete
Then on the right select Change
Then in the lower right select Commit Changes
option #3 update them manually as you are doing now