Actuals remain at zero when activity started and a perecnt complete applied.

Member for

16 years 3 months

yeah I think I said that but there is mote to that than just that other setting to adjust 

Member for

17 years 4 months

Hi David,

try updating the duration percent, it will drive the actual untis to change automatically.

If the setting is physical percent, always you have to manually input the actual values.

BR

Kannan

Member for

16 years 3 months

at the project level make sure that you project is open and highlighted

on the calculations tab make sure that on the right under resource assignments that when updating actual units or costs that Subtract Actual from at completion is checked

make sure that re-calculate actual units and cost when duration % complete changes 

make sure that Link actual and actual this period units and costs is checked 

The problem here is that you are using physical % complete and updating actuals is based on duration % complete

you have 3 options 

option #1 change the % complete type to Duration

option #2 run a global change 

where Physical % complete is not equal to 0

then Duration % Complete = Physical % complete

Then on the right select Change 

Then in the lower right select Commit Changes

option #3 update them manually as you are doing now