P6 Remaining Units not equal to Budgeted Units

Member for

6 years 7 months

yes

Member for

16 years 3 months

make sure that at the projects level under the calculations tab that on the left under Activities that Link Budget and At completion for not started activities IS CHECKED

Member for

6 years 7 months

Hi Zoltan,

 i am having this issue with the not started Activities.

Member for

6 years 7 months

Hi Zoltan,

 i am having this issue with the not started Activities.

Member for

6 years 7 months

Hi Zoltan,

 i am having this issue with the not started Activities.

Member for

6 years 7 months

Hi Zoltan,

 i am having this issue with the not started Activities.

Member for

16 years 3 months

they never will be you budgeted units is just that once your start to progress the schedule the remaining units wil be reduced and when the activity is done the remaining units will be 0

Member for

6 years 7 months

hi, Emma,

I checked that, its already marked.

in all the project they are equal except for the coming two months.

Regards,

 

 

Member for

9 years 3 months

Hi Ahmad, 

Have you tried this:

In the Projects Window, in the Calculations tab - do you have "Link Budget and At Completion for non started Activities"  checked?

 

I'm sure that worked for me.

Member for

6 years 7 months

hi

I have almost the same problem, the budgeted units for the non started activities are more than the remaining 

Link Budget and At Completion for non started Activities"  is checked

what might be wrong??

Member for

9 years 3 months

Hi David, just checked that and it worked. Thanks

Member for

21 years

In the Projects Window, in the Calculations tab - do you have "Link Budget and At Completion for non started Activities"  checked?