make sure that at the projects level under the calculations tab that on the left under Activities that Link Budget and At completion for not started activities IS CHECKED
they never will be you budgeted units is just that once your start to progress the schedule the remaining units wil be reduced and when the activity is done the remaining units will be 0
Member for
6 years 7 monthsyes
yes
Member for
16 years 3 monthsmake sure that at the
make sure that at the projects level under the calculations tab that on the left under Activities that Link Budget and At completion for not started activities IS CHECKED
Member for
6 years 7 monthsHi Zoltan, i am having this
Hi Zoltan,
i am having this issue with the not started Activities.
Member for
6 years 7 monthsHi Zoltan, i am having this
Hi Zoltan,
i am having this issue with the not started Activities.
Member for
6 years 7 monthsHi Zoltan, i am having this
Hi Zoltan,
i am having this issue with the not started Activities.
Member for
6 years 7 monthsHi Zoltan, i am having this
Hi Zoltan,
i am having this issue with the not started Activities.
Member for
16 years 3 monthsthey never will be you
they never will be you budgeted units is just that once your start to progress the schedule the remaining units wil be reduced and when the activity is done the remaining units will be 0
Member for
6 years 7 monthshi, Emma,I checked that, its
hi, Emma,
I checked that, its already marked.
in all the project they are equal except for the coming two months.
Regards,
Member for
9 years 3 monthsHi Ahmad, Have you tried
Hi Ahmad,
Have you tried this:
In the Projects Window, in the Calculations tab - do you have "Link Budget and At Completion for non started Activities" checked?
I'm sure that worked for me.
Member for
6 years 7 monthshiI have almost the same
hi
I have almost the same problem, the budgeted units for the non started activities are more than the remaining
Link Budget and At Completion for non started Activities" is checked
what might be wrong??
Member for
9 years 3 monthsHi David, just checked that
Hi David, just checked that and it worked. Thanks
Member for
21 yearsIn the Projects Window, in
In the Projects Window, in the Calculations tab - do you have "Link Budget and At Completion for non started Activities" checked?