Is there any Relationship b/w Performance% complete value & Total float value.....???

Member for

10 years 7 months

Thanxs zahid...

 

Member for

9 years 2 months

1) Schedule % complete is calculated in P6 wrt to Baseline Planned dates and Data Date.

Eg: Activity start and finish are 22-Dec-17 to 2-Jan18 i.e. duration is 12 days. When data date is 25-Dec-17, (22-Dec-17)-(25-Dec-17)=4days. Schedule % will be 4days/12 days = 27%. For data Date 29-Dec-17. Schedule % will be 64%.

 

2) For Performance %; It is calculated wrt to Duration % complete/Units % complete/Physical % complete, depending on how the progress is being recorded. I.e Performance % complete is = Duration % complete (assuming that the project is resource loaded)

Member for

10 years 7 months

Thanks for your response.

I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

Member for

10 years 7 months

Thanks for your response.

I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

Member for

16 years 3 months

how are you measuring the performance ?