1) Schedule % complete is calculated in P6 wrt to Baseline Planned dates and Data Date.
Eg: Activity start and finish are 22-Dec-17 to 2-Jan18 i.e. duration is 12 days. When data date is 25-Dec-17, (22-Dec-17)-(25-Dec-17)=4days. Schedule % will be 4days/12 days = 27%. For data Date 29-Dec-17. Schedule % will be 64%.
2) For Performance %; It is calculated wrt to Duration % complete/Units % complete/Physical % complete, depending on how the progress is being recorded. I.e Performance % complete is = Duration % complete (assuming that the project is resource loaded)
Member for
10 years 7 months
Member for10 years8 months
Submitted by abubakar munir on Sun, 2017-12-24 07:07
Member for
10 years 7 monthsThanxs zahid...
Thanxs zahid...
Member for
9 years 2 months1) Schedule % complete is
1) Schedule % complete is calculated in P6 wrt to Baseline Planned dates and Data Date.
Eg: Activity start and finish are 22-Dec-17 to 2-Jan18 i.e. duration is 12 days. When data date is 25-Dec-17, (22-Dec-17)-(25-Dec-17)=4days. Schedule % will be 4days/12 days = 27%. For data Date 29-Dec-17. Schedule % will be 64%.
2) For Performance %; It is calculated wrt to Duration % complete/Units % complete/Physical % complete, depending on how the progress is being recorded. I.e Performance % complete is = Duration % complete (assuming that the project is resource loaded)
Member for
10 years 7 monthsThanks for your response. I
Thanks for your response.
I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.
Waiting for your reply.
Member for
10 years 7 monthsThanks for your response. I
Thanks for your response.
I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.
Waiting for your reply.
Member for
16 years 3 monthshow are you measuring the
how are you measuring the performance ?