With the improved image, it is easy to see your problem. Task ID 2 "Determine proj" is a half-day task ending mid-day on 29Feb'16. It's string of successors then start and finish at mid-day.
This is normal behavior whenever you introduce partial-day durations.
Member for
12 years 2 months
Member for12 years2 months
Submitted by ss.dhatwalia on Thu, 2017-12-14 11:40
The image you posted is illegible. In the General Options, choose a Date format that includes the time of day. That will demonstrate your task starting at mid-day on 01Mar'16 and finishing at mid-day on 02Mar'16. You must review the logic to see why this is the case.
Member for
12 years 2 monthsThanks a lot!
Thanks a lot!
Member for
18 years 11 monthsShishir,With the improved
Shishir,
With the improved image, it is easy to see your problem. Task ID 2 "Determine proj" is a half-day task ending mid-day on 29Feb'16. It's string of successors then start and finish at mid-day.
This is normal behavior whenever you introduce partial-day durations.
Member for
12 years 2 monthsThank you for your time. I
Thank you for your time. I have updated the enlarged Image. As you mentioned, I added the Time in the
Options - General - Date Format but it is not helping. It is showing Time along with the Date.
Member for
18 years 11 monthsShishir,The image you posted
Shishir,
The image you posted is illegible. In the General Options, choose a Date format that includes the time of day. That will demonstrate your task starting at mid-day on 01Mar'16 and finishing at mid-day on 02Mar'16. You must review the logic to see why this is the case.