Duration is showing One day but showing two days in Task Usage

Member for

12 years 2 months

Thanks a lot!

Member for

18 years 11 months

Shishir,

With the improved image, it is easy to see your problem.  Task ID 2 "Determine proj" is a half-day task ending mid-day on 29Feb'16.  It's string of successors then start and finish at mid-day.

This is normal behavior whenever you introduce partial-day durations.  

Member for

12 years 2 months

Thank you for your time. I have updated the enlarged Image. As you mentioned, I added the Time in the

Options - General - Date Format but it is not helping. It is showing Time along with the Date. 

Member for

18 years 11 months

Shishir,

The image you posted is illegible.  In the General Options, choose a Date format that includes the time of day.  That will demonstrate your task starting at mid-day on 01Mar'16 and finishing at mid-day on 02Mar'16.  You must review the logic to see why this is the case.