Resources with no budget, but a cost to complete

Member for

22 years 3 months

Steven



At the project level, select the ’Calculations’ tab and untick the ’Link Budget and At Completion for not started activities’.



Doing this allowed me to have a remaining cost with a zero budget and also allowed a remaining duration to be different from original duration for non started activities.



Regards

Member for

23 years

Unfortunately not. On a similar note, if you reduce the remaining duration of an activity that hasnt started, P3e automatically reduces the Original Duration. This isnt always the desired effect.

Member for

22 years 3 months

Steven



Something to try - in the resource assignment detail of the activity, insert a ’Cost Units Linked’ field and untick the box.



Regards