updating hammock task in MSP 2007

Member for

20 years 7 months

kp,

You can do this but it is not straightforward.

You can copy a cell in MSP and then paste the content as a link into another cell (through paste special, paste link)

Just copying a date into the destination cell won't work because that will normally just impose a constraint and not change the duration.

Cleaver use of formula's in combination with the above links will probably get you there, but remember MSP gets 'nervous' from these links as it keeps recalculating/updating continuously.

H.T.H.