Hai

1.Negative Float is not Applicable in baseline

2.It may be Schedule Statistics Report and not Schedule Matrix Report what we will see after scheduling

1.Schedule Option

2.Schedule Statistics

3.Open End listing

4.Critical Activity

5.Milestone

etc

If  Schedule Matrix is correct then i dont have any idea

Regards

Anbin