Project Services Career Issues Member for 19 years 10 months Member for 19 years 10 months Submitted by Tanveer Ahmad Niazi on Sun, 2010-12-26 14:31 Permalink Hi Anbin Ponnith Thank you Hi Anbin Ponnith Thank you very much for your reply Tanveer Member for 16 years 4 months Member for 16 years 5 months Submitted by Anbin Ponnith on Sun, 2010-12-26 11:14 Permalink Hai 1.Negative Float is not Hai 1.Negative Float is not Applicable in baseline 2.It may be Schedule Statistics Report and not Schedule Matrix Report what we will see after scheduling 1.Schedule Option 2.Schedule Statistics 3.Open End listing 4.Critical Activity 5.Milestone etc If Schedule Matrix is correct then i dont have any idea Regards Anbin Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Tanveer Ahmad Niazi on Sun, 2010-12-26 14:31 Permalink Hi Anbin Ponnith Thank you Hi Anbin Ponnith Thank you very much for your reply Tanveer
Member for 16 years 4 months Member for 16 years 5 months Submitted by Anbin Ponnith on Sun, 2010-12-26 11:14 Permalink Hai 1.Negative Float is not Hai 1.Negative Float is not Applicable in baseline 2.It may be Schedule Statistics Report and not Schedule Matrix Report what we will see after scheduling 1.Schedule Option 2.Schedule Statistics 3.Open End listing 4.Critical Activity 5.Milestone etc If Schedule Matrix is correct then i dont have any idea Regards Anbin
Member for
19 years 10 monthsHi Anbin Ponnith Thank you
Hi Anbin Ponnith
Thank you very much for your reply
Tanveer
Member for
16 years 4 monthsHai 1.Negative Float is not
Hai
1.Negative Float is not Applicable in baseline
2.It may be Schedule Statistics Report and not Schedule Matrix Report what we will see after scheduling
1.Schedule Option
2.Schedule Statistics
3.Open End listing
4.Critical Activity
5.Milestone
etc
If Schedule Matrix is correct then i dont have any idea
Regards
Anbin