P3 technical glitch

Member for

22 years 10 months

 Edgar,

This sounds like a set-up for Halloween; the Slowly Disappearing Activities.  If this is not the case, then I suspect corrupt schedule files.  Run the program C:\P3WIN\P3PROGS\PFXW.exe, select your ‘cursed’ schedule, select all option boxes in the lower left and then Run.  After that, I would recommend using P3 to copy the schedule and use the copy.  Good luck!

Member for

21 years 8 months

Run  your schedule and from the schedule report look for finish constraints, can be in any of two ways, either a must finish date for the job or a finish constraint at the individual activity level.

Perhaps the constraints got them back in time on your last schedule run and this is why they seem disappeared.

Member for

20 years

Thanks for the response, Mai.

I have utilized both WBS & Activity codes so I can organize it either way. I think I have done all the necessary checking including the one you suggested and it still doesn't solve the problem.

Im sure there's one particular solution available I just don't know what is it.... i think the solution lies on this info "the data date is 18 October 2010 but the early finish is 08 Dec 08" as seen from the overview.

Once again thanks.

Member for

15 years 8 months

Hi:

 

Your program is it WBS or Activities cods?

if it is WBS please do, check the Organize set up from Format...

 

Mai