This sounds like a set-up for Halloween; the Slowly Disappearing Activities. If this is not the case, then I suspect corrupt schedule files. Run the program C:\P3WIN\P3PROGS\PFXW.exe, select your ‘cursed’ schedule, select all option boxes in the lower left and then Run. After that, I would recommend using P3 to copy the schedule and use the copy. Good luck!
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Thu, 2010-10-21 11:39
Run your schedule and from the schedule report look for finish constraints, can be in any of two ways, either a must finish date for the job or a finish constraint at the individual activity level.
Perhaps the constraints got them back in time on your last schedule run and this is why they seem disappeared.
I have utilized both WBS & Activity codes so I can organize it either way. I think I have done all the necessary checking including the one you suggested and it still doesn't solve the problem.
Im sure there's one particular solution available I just don't know what is it.... i think the solution lies on this info "the data date is 18 October 2010 but the early finish is 08 Dec 08" as seen from the overview.
Member for
22 years 10 monthsEdgar, This sounds like a
Edgar,
This sounds like a set-up for Halloween; the Slowly Disappearing Activities. If this is not the case, then I suspect corrupt schedule files. Run the program C:\P3WIN\P3PROGS\PFXW.exe, select your ‘cursed’ schedule, select all option boxes in the lower left and then Run. After that, I would recommend using P3 to copy the schedule and use the copy. Good luck!
Member for
21 years 8 monthsRun your schedule and from
Run your schedule and from the schedule report look for finish constraints, can be in any of two ways, either a must finish date for the job or a finish constraint at the individual activity level.
Perhaps the constraints got them back in time on your last schedule run and this is why they seem disappeared.
Member for
20 yearsThanks for the response,
Thanks for the response, Mai.
I have utilized both WBS & Activity codes so I can organize it either way. I think I have done all the necessary checking including the one you suggested and it still doesn't solve the problem.
Im sure there's one particular solution available I just don't know what is it.... i think the solution lies on this info "the data date is 18 October 2010 but the early finish is 08 Dec 08" as seen from the overview.
Once again thanks.
Member for
15 years 8 monthsHi: Your program is it WBS
Hi:
Your program is it WBS or Activities cods?
if it is WBS please do, check the Organize set up from Format...