How to Generate Cash Flow in P3

Member for

19 years

Irfan,

Use Tools-> Graphic Reports-> Resource & Cost-> RC03 commulative and Monthly Cost. Change the date on the date tab and resource selection should be EQ ????????????

That will use all resources define on your projects.

Member for

16 years 3 months

Thanks for reply Rodel,



I got it what u explained in ur last post. But same thing I want to generate from Tools>Graphic Reports>Resource & Cost>.



But when I m going to resource selection which is > Group if = EQ > Low Value Resource = My resource what I assigned > after selection of dates, curves etc. when I m running it is showing just periods or nothing.



So pls can u help me again……



Thanks……..




Member for

19 years

Irfan,

Like what I have said, Ctrl+F7, This will display Resource Profile histogram and S-Curve.

On the Resource Profile dialog box under resource select Total and click Display. Under Display tick Cost and it should display cost S-Curve and histogram.

Member for

16 years 3 months

thanks rodel,



wht i did i want to explain, i add one resource name cost and pick all activities and apply resource assignment. Than i pick each activity and assign its cost from Budget > Budget Summary > Budget Amount under Cost Catogery.



But these costs not coming in my resource Curve.



Pls tell me how to generate S-Curve..





thanks,,,

Member for

19 years

Irfan,

Ctrl + F7 or View-> Resource Profile or click the icon Resource/Cost Profile



That will show Profile and S-curve in P3.