Use Tools-> Graphic Reports-> Resource & Cost-> RC03 commulative and Monthly Cost. Change the date on the date tab and resource selection should be EQ ????????????
That will use all resources define on your projects.
I got it what u explained in ur last post. But same thing I want to generate from Tools>Graphic Reports>Resource & Cost>.
But when I m going to resource selection which is > Group if = EQ > Low Value Resource = My resource what I assigned > after selection of dates, curves etc. when I m running it is showing just periods or nothing.
So pls can u help me again……
Thanks……..
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Sun, 2010-06-27 05:57
Like what I have said, Ctrl+F7, This will display Resource Profile histogram and S-Curve.
On the Resource Profile dialog box under resource select Total and click Display. Under Display tick Cost and it should display cost S-Curve and histogram.
wht i did i want to explain, i add one resource name cost and pick all activities and apply resource assignment. Than i pick each activity and assign its cost from Budget > Budget Summary > Budget Amount under Cost Catogery.
But these costs not coming in my resource Curve.
Pls tell me how to generate S-Curve..
thanks,,,
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Sun, 2010-06-27 03:26
Member for
19 yearsRE: How to Generate Cash Flow in P3
Irfan,
Use Tools-> Graphic Reports-> Resource & Cost-> RC03 commulative and Monthly Cost. Change the date on the date tab and resource selection should be EQ ????????????
That will use all resources define on your projects.
Member for
16 years 3 monthsRE: How to Generate Cash Flow in P3
Thanks for reply Rodel,
I got it what u explained in ur last post. But same thing I want to generate from Tools>Graphic Reports>Resource & Cost>.
But when I m going to resource selection which is > Group if = EQ > Low Value Resource = My resource what I assigned > after selection of dates, curves etc. when I m running it is showing just periods or nothing.
So pls can u help me again……
Thanks……..
Member for
19 yearsRE: How to Generate Cash Flow in P3
Irfan,
Like what I have said, Ctrl+F7, This will display Resource Profile histogram and S-Curve.
On the Resource Profile dialog box under resource select Total and click Display. Under Display tick Cost and it should display cost S-Curve and histogram.
Member for
16 years 3 monthsRE: How to Generate Cash Flow in P3
thanks rodel,
wht i did i want to explain, i add one resource name cost and pick all activities and apply resource assignment. Than i pick each activity and assign its cost from Budget > Budget Summary > Budget Amount under Cost Catogery.
But these costs not coming in my resource Curve.
Pls tell me how to generate S-Curve..
thanks,,,
Member for
19 yearsRE: How to Generate Cash Flow in P3
Irfan,
Ctrl + F7 or View-> Resource Profile or click the icon Resource/Cost Profile
That will show Profile and S-curve in P3.