Claim

Member for

18 years 5 months

Check ur tender validity dates



This is a general scenario in govt. sector in this part of the world and as client, they do ask to increase the validity of the tender submitted from time to time through official letters.



Check the validity of the tender rates and as sameer suggested u can put ur claim

Member for

17 years 3 months

Dear Bal,



It depends on the Contract Conditions. If it is a FIDIC contract, then the latest Date of Commencement is 42 days after the signing of the agreement.



You should have submitted a Program of Works within 28 days from that date (June 18) showing the scope of works and date of completion.



Then you do a delay analysis by showing the results of the following:



Agreement: May 8, 2008

+42 days

Commencement Date: June 18, 2008

Actual start of work at site: October 05, 2008

Critical Activity path delayed by: 109 days



You have to check your contract and the compensation claused for actions that you can take.



Good luck,