Resource Loading

Member for

18 years 5 months

My advise wud be 2 use global change, if no. of activities are more.



If: actvity contains xxxx,



then AD res value.



&



Then follow-up above for loading budgeted Quantity.



Cheers,

Member for

18 years 3 months

view menu-->activity detail-->resource (or control R) can be seen on right click also..

also,by using insert menu-->resource assignments (or click toolbar icon)



another way by export/import method and global change which will be easier if you become familiar with using it