Primavera Project Planner - P3 Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2008-07-23 00:54 Permalink RE: Resource Loading My advise wud be 2 use global change, if no. of activities are more. If: actvity contains xxxx, then AD res value. & Then follow-up above for loading budgeted Quantity. Cheers, Member for 18 years 3 months Member for 18 years 3 months Submitted by PINAN T. on Tue, 2008-07-22 23:25 Permalink RE: Resource Loading view menu-->activity detail-->resource (or control R) can be seen on right click also.. also,by using insert menu-->resource assignments (or click toolbar icon) another way by export/import method and global change which will be easier if you become familiar with using it Log in or register to post comments
Member for 18 years 5 months Member for 18 years 5 months Submitted by A D on Wed, 2008-07-23 00:54 Permalink RE: Resource Loading My advise wud be 2 use global change, if no. of activities are more. If: actvity contains xxxx, then AD res value. & Then follow-up above for loading budgeted Quantity. Cheers,
Member for 18 years 3 months Member for 18 years 3 months Submitted by PINAN T. on Tue, 2008-07-22 23:25 Permalink RE: Resource Loading view menu-->activity detail-->resource (or control R) can be seen on right click also.. also,by using insert menu-->resource assignments (or click toolbar icon) another way by export/import method and global change which will be easier if you become familiar with using it
Member for
18 years 5 monthsRE: Resource Loading
My advise wud be 2 use global change, if no. of activities are more.
If: actvity contains xxxx,
then AD res value.
&
Then follow-up above for loading budgeted Quantity.
Cheers,
Member for
18 years 3 monthsRE: Resource Loading
view menu-->activity detail-->resource (or control R) can be seen on right click also..
also,by using insert menu-->resource assignments (or click toolbar icon)
another way by export/import method and global change which will be easier if you become familiar with using it