P3 will give you upfront planned manpower report if your baseline program and related activities were already allocated with the required manpower/resources. P3 tabulated/graphical reports can be utilize to compare actual vs. planned.
Default formulas are already encoded on the software for this purpose.
Member for
17 yearsHi Dear,First you can take
Hi Dear,
First you can take the Project details and Productivities rate for all materials so you can get easily loading to programme
Jaffer
Member for
20 years 7 monthsRE: Manpower loading
Hi Uly,
Common, dont get it wrong, will you!of course im fortunate that someone answered my query, im thankful about it."kalas"
Burley, thank you again pare.....and thank you Uly.
my two cents
Member for
20 years 2 monthsRE: Manpower loading
Hi Uly,
Keep the ship afloat... problem solved.
Burley
Member for
20 years 2 monthsRE: Manpower loading
You said;`unfortunately, i already settled the problem.
So,you mean; you are not fortunate because you solve your problem.
Member for
20 years 7 monthsRE: Manpower loading
Hi Guyz,
Thank you guyz for answering, unfortunately, i already settled the problem.
Thanks Again.
Member for
20 years 2 monthsRE: Manpower loading
Hi Ric,
P3 will give you upfront planned manpower report if your baseline program and related activities were already allocated with the required manpower/resources. P3 tabulated/graphical reports can be utilize to compare actual vs. planned.
Default formulas are already encoded on the software for this purpose.
Cheers,
Burley
Member for
19 years 1 monthRE: Manpower loading
it all depends on your knowledge of the job or the tasks! how can you allocate resources if you dont even know how to do the job?!!!
Member for
21 years 3 monthsRE: Manpower loading
Hi!
Rick it all depands on the requirement of the report to be given to your management
hope u got it!!