Manpower loading

Member for

17 years

Hi Dear,

First you can take the Project details and Productivities rate for all materials so you can get easily loading to programme

Jaffer

Member for

20 years 7 months

Hi Uly,



Common, don’t get it wrong, will you!of course i’m fortunate that someone answered my query, i’m thankful about it."kalas"

Burley, thank you again pare.....and thank you Uly.



my two cents


Member for

20 years 2 months

Hi Uly,



Keep the ship afloat... problem solved.



Burley

Member for

20 years 2 months



You said;`unfortunately, i already settled the problem.



So,you mean; you are not fortunate because you solve your problem.

Member for

20 years 7 months



Hi Guyz,

Thank you guyz for answering, unfortunately, i already settled the problem.



Thanks Again.


Member for

20 years 2 months

Hi Ric,



P3 will give you upfront planned manpower report if your baseline program and related activities were already allocated with the required manpower/resources. P3 tabulated/graphical reports can be utilize to compare actual vs. planned.



Default formulas are already encoded on the software for this purpose.



Cheers,



Burley

Member for

19 years 1 month

it all depends on your knowledge of the job or the tasks! how can you allocate resources if you don’t even know how to do the job?!!!

Member for

21 years 3 months

Hi!



Rick it all depands on the requirement of the report to be given to your management



hope u got it!!