These are numbers allocated for the unique activity in the cycle time.
Say for procurement i allocate IDs like 101, 103, 105, 107
For Engg., 001, 003, 005, 007
For Installation, 201, 203, 205
First seven alphabets/nos. can be used with upper level of WBS/activity codes. This will help you to identify/filter activities much better.
This is my practice again. You can change it as you want. You can have 4 nos also, but sometimes you struggle with acivity ID , as only 10 digits can be allocated for creating avtivity ID (In p3.1 at least)
Cheers,
Raviraj A Bhedase
Member for
18 years 9 months
Member for18 years9 months
Submitted by Pranab Kumar Deb on Thu, 2007-06-14 03:46
i suggest that you need to turn your back from p3 into primavera P5 . your problem will be solve as easy as feeding chicken.
In a complicated world using p3 fragnet it will be more convinient to use MMD methology management then link it to primavera P5 or to make onself easy use excel . imp/ex.
Excellent idea!!!!!!! The only thing I need to do is to re-develop my project using fragnets. But, correct me if I am wrong, I need to change the activity codes for repeated activities each time I retrieve a fragnet. I mean, activity codes contain location information which will be copied exactly the way I have in fragnet.
Member for
18 years 5 months
Member for18 years6 months
Submitted by Ashraf Jahangeer on Sun, 2007-06-10 08:28
Instead of jotting down 600 activities in P3 and then linking them, the best way to do is to first create a activtity cycle. Say a cycle of 30 activities for one floor and then repeating these activties. You can store that as fragnet.
Then you can link floor-to-floor activities.
Same you can repeat for structures / MEP / Cladding and other finishing items.
Member for
19 years 10 monthsHi Lothar Good sales pitch
Hi Lothar
Good sales pitch even if the topic was 5 years old.
Best regards
Mike Testro
Member for
18 years 5 monthsRE: Network Diagram
These are numbers allocated for the unique activity in the cycle time.
Say for procurement i allocate IDs like 101, 103, 105, 107
For Engg., 001, 003, 005, 007
For Installation, 201, 203, 205
First seven alphabets/nos. can be used with upper level of WBS/activity codes. This will help you to identify/filter activities much better.
This is my practice again. You can change it as you want. You can have 4 nos also, but sometimes you struggle with acivity ID , as only 10 digits can be allocated for creating avtivity ID (In p3.1 at least)
Cheers,
Raviraj A Bhedase
Member for
18 years 9 monthsRE: Network Diagram
Hello Raviraj,
Can you explain what is the motive of keeping the last 3 digits alone in the activity field.
regards
deb
Member for
18 years 5 monthsRE: Network Diagram
THe most easy way i do is to have (Works better than fragnet):
copy the cycle time (group of activity with relationships defined). Note: In the cycle time, keep only the last three digits in the activity field.
Filter -> No activities
It will ask for three options for renaming activities:
- Rename all
- Prefix / sufix
- Auto-increment
Click on prefix and enter OK.
Type in the activity ID required
and then filter it for all activities.
Re-organize it.
Thats it.
This is most fast and easy way for adding activities.
Cheers,
Raviraj A Bhedase
Member for
18 years 4 monthsRE: Network Diagram
Hi Ravi
Thanks for your email with some valuable infomation on FRAGNETS.
Member for
20 years 2 monthsRE: Network Diagram
Hi,
i suggest that you need to turn your back from p3 into primavera P5 . your problem will be solve as easy as feeding chicken.
In a complicated world using p3 fragnet it will be more convinient to use MMD methology management then link it to primavera P5 or to make onself easy use excel . imp/ex.
Member for
18 years 5 monthsRE: Network Diagram
Hi Ashraf / Sajid,
I have a good paper on using fragnets.
send me a mail on ravirajab@yahoo.co.in
Cheers,
Raviraj
Member for
18 years 4 monthsRE: Network Diagram
Hi Ravi
Excellent idea!!!!!!! The only thing I need to do is to re-develop my project using fragnets. But, correct me if I am wrong, I need to change the activity codes for repeated activities each time I retrieve a fragnet. I mean, activity codes contain location information which will be copied exactly the way I have in fragnet.
Member for
18 years 5 monthsRE: Network Diagram
Ravi,
Excellent idea...can you explain a bit more on using Fragnet.
In fact I have never used it, I used excel for repetitive type of activities and then import these files into P3 project.
Regards,
Ashraf
Member for
18 years 5 monthsRE: Network Diagram
Instead of jotting down 600 activities in P3 and then linking them, the best way to do is to first create a activtity cycle. Say a cycle of 30 activities for one floor and then repeating these activties. You can store that as fragnet.
Then you can link floor-to-floor activities.
Same you can repeat for structures / MEP / Cladding and other finishing items.
Cheers,
Raviraj
Member for
18 years 4 monthsRE: Network Diagram
Forgot to mention that I am on p3.