undo command

Member for

20 years

Ifeanyi Olike;



P3e an P5 are not the same and there is no P3e ver 5.



The correct name is Primavera 5.0 (official name informed by Primavera Systems) an P5 is an abbreviation for Primavera 5.0.



P3e is an abbreviation for Primavera Project Planner for the Enterprise and its last varsion was 4.1. There is no P3e any more.



Regards.

Member for

19 years

P3e/P3ec came first as ver 4/4.1 then P3e ver5. All of them are the same but some country they call it differenly and not by version.

Member for

18 years 9 months

Rodel,



I thought P3e and P5 are the same. Or are they different?


Member for

19 years

Yap! I been using this since and now upgraded to P5 and its working fine.

Member for

22 years 9 months

Rodel,

is undo REALLY available since P3e? I had in mind that it had come only with P5

Alexandre

Member for

19 years

Undo command is only available in P3e or P5. If you haven’t save, schedule, or press F5 to save your changes you can undo it by pressing Ctrl "Z" up to the last changes.

Member for

22 years 9 months

Hi,

there is NO undo command in P3!

Alexandre