Scheduling P3 and the activities stay where they are?!

Member for

19 years

if not mistaken.. there is an option to "apply" the datadate from the master to all the subs, when u schedle from the master.



can someone confirm?



long time didnt use subproj....

Member for

19 years 7 months

I’ve been a bit dim, we’ve got sub projects and I thought that by scheduling the overall project it would move the data dates for all the subs...



Having now scheduled the subs all is happy!

Member for

22 years 1 month

It’s strange but one possible reason is the option that you choose to apply when scheduling activities.



Check this: instead of pressing F9 go to ’Tools’ --->> ’Schedule’ --->> ’Options’. Select the ’General’ tab under "When scheduling activities apply" select ’Progress Override’. Then schedule.



If you select ’Retained Logic’ it could create the kind of scenario that you presented.



When you choose Progress Override, P3 ignores the relationship (logic) and allow the activity to be rescheduled.



Please just check it out and let me have your feedback.





Akin Adurosakin

Nigeria