It’s strange but one possible reason is the option that you choose to apply when scheduling activities.
Check this: instead of pressing F9 go to Tools --->> Schedule --->> Options. Select the General tab under "When scheduling activities apply" select Progress Override. Then schedule.
If you select Retained Logic it could create the kind of scenario that you presented.
When you choose Progress Override, P3 ignores the relationship (logic) and allow the activity to be rescheduled.
Please just check it out and let me have your feedback.
Member for
19 yearsRE: Scheduling P3 and the activities stay where they are?!
if not mistaken.. there is an option to "apply" the datadate from the master to all the subs, when u schedle from the master.
can someone confirm?
long time didnt use subproj....
Member for
19 years 7 monthsRE: Scheduling P3 and the activities stay where they are?!
Ive been a bit dim, weve got sub projects and I thought that by scheduling the overall project it would move the data dates for all the subs...
Having now scheduled the subs all is happy!
Member for
19 years 1 monthRE: Scheduling P3 and the activities stay where they are?!
check activies with constraints
Member for
19 years 7 monthsRE: Scheduling P3 and the activities stay where they are?!
Thanks for your responses chaps, tried and checked both but sadly no fix!
Weve sent a prx to Primavera so well see what they come back with...
Member for
19 yearsRE: Scheduling P3 and the activities stay where they are?!
possibly you are NOT viewing current bar (ES/EF)
but viewing baseline (T1ES/T1EF)?
Member for
22 years 1 monthRE: Scheduling P3 and the activities stay where they are?!
It’s strange but one possible reason is the option that you choose to apply when scheduling activities.
Check this: instead of pressing F9 go to Tools --->> Schedule --->> Options. Select the General tab under "When scheduling activities apply" select Progress Override. Then schedule.
If you select Retained Logic it could create the kind of scenario that you presented.
When you choose Progress Override, P3 ignores the relationship (logic) and allow the activity to be rescheduled.
Please just check it out and let me have your feedback.
Akin Adurosakin
Nigeria