Auto Link ???? (Multiple Activites to Same Successor)

Member for

19 years 9 months

Sami

As to import from Excel, you must create a DBF file with feilds of "ACT" as the first column where you list Activity IDs of all the activities to which you wish to add the common successor to. In the second column you must have "SUC" as the field data where you will fill the common completion Activity ID. In addition you must have Fields of "LAG" which must be ’0’ and ’REL’ which must be ’FS’ for all the activities.

Regards

Member for

23 years

I Persume You Want To Link A Group Of Activities To One Activity Or Milestone As Predecessers And You Dont Know Linking Data With Excel

Try This



First Link Manualy to One Predecessor

Open The Activity Form

Open Successor Form

Select The Linked Activity ( From Group Of Activities )

You Will See In the Form the ID of Successor

Now Copy That Actvity ID



Select another Activiity

Paste Acivity ID in The Succsessor Form

Click Another Activity

Go On




Member for

19 years 2 months

Dear Dayanidhi





My problrm that these activites are not linked at all to any successo so I made a completion activity which i want to link them to thats it !! have you got the picture

by the way it was a qustion too how can i export those info to excel







thnx



sami