It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.
remaining things look for the other post.
Member for
19 years 7 months
Member for19 years7 months
Submitted by Karim Mounir on Thu, 2006-11-23 02:23
Member for
18 years 11 monthsRE: Progress Override
Thank you so much! That article is very informative.
Member for
22 years 7 monthsRE: Progress Override
Hi Elizabeth,
It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.
remaining things look for the other post.
Member for
19 years 7 monthsRE: Progress Override
Hi Elizabeth,
You can checkout this address for more information about Retained Logic & Progress Override:
http://www.pmicos.org/topics/aug2003.asp
And You can choose the method of scheduling from:
"Tools"-->"Schedule"-->"Options"
Regards.