Thank you so much! That article is very informative.

Member for

22 years 7 months

Hi Elizabeth,



It is not logic override, that is retained logic, anyhow to access progress over ride, go to Tools->Schedule(Don’t press F9)->Options->look for progress override to check that option under the item when scheduling activities apply.



remaining things look for the other post.

Member for

19 years 7 months

Hi Elizabeth,



You can checkout this address for more information about Retained Logic & Progress Override:

http://www.pmicos.org/topics/aug2003.asp



And You can choose the method of scheduling from:

"Tools"-->"Schedule"-->"Options"



Regards.