you can display the activity report #6; this report uses the filter "shifted activities" (I am not sure of the exact english name,as I am using the french version of MSP).
it is also possible to create a similar report and associate another filter displaying only the activities the status of which is relevant for you.
All the best,
Alexandre
Member for
19 years 1 month
Member for19 years2 months
Submitted by Tolulope Areo on Sat, 2006-09-30 05:13
hello, if you need to know the no of days an activity is delayed,or being overlapped, you can always true task inforation for neccessary confirmation......Tolu Areo
Member for
19 years 2 monthsRE: Activities progress
Thks for help guys
Member for
22 years 9 monthsRE: Activities progress
Hello Adrian,
you can display the activity report #6; this report uses the filter "shifted activities" (I am not sure of the exact english name,as I am using the french version of MSP).
it is also possible to create a similar report and associate another filter displaying only the activities the status of which is relevant for you.
All the best,
Alexandre
Member for
19 years 1 monthRE: Activities progress
hello, if you need to know the no of days an activity is delayed,or being overlapped, you can always true task inforation for neccessary confirmation......Tolu Areo