Activities progress

Member for

19 years 2 months

Thks for help guys

Member for

22 years 9 months

Hello Adrian,

you can display the activity report #6; this report uses the filter "shifted activities" (I am not sure of the exact english name,as I am using the french version of MSP).

it is also possible to create a similar report and associate another filter displaying only the activities the status of which is relevant for you.

All the best,

Alexandre

Member for

19 years 1 month

hello, if you need to know the no of days an activity is delayed,or being overlapped, you can always true task inforation for neccessary confirmation......Tolu Areo