Activities not started against scheduled

Member for

19 years 3 months

Hi Steeven,



This way it is correct, but some more



If compaire VARIANCE TARGET-1 Es & EF with

VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float)



Filter is like:



Level-1



VARIANCE TARGET-1 EARLY START - LT- 0



Level-2



Actual Dates -WR- Project Start date to data date (update)



Level-3



%age Complete -WR - 1-99

Member for

22 years 11 months

Depends on the software you are using.

P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful.

Member for

20 years 7 months

Use Filter with Percent complete is equal to zero which will give you activities not started in your update.