Forensic Claims Analysis Member for 19 years 3 months Member for 19 years 3 months Submitted by Giji Thomas on Tue, 2006-08-15 09:58 Permalink RE: Activities not started against scheduled Hi Steeven, This way it is correct, but some more If compaire VARIANCE TARGET-1 Es & EF with VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float) Filter is like: Level-1 VARIANCE TARGET-1 EARLY START - LT- 0 Level-2 Actual Dates -WR- Project Start date to data date (update) Level-3 %age Complete -WR - 1-99 Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Tue, 2006-08-15 09:04 Permalink RE: Activities not started against scheduled Depends on the software you are using. P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful. Member for 20 years 7 months Member for 20 years 7 months Submitted by Sunil Kumar on Sun, 2006-08-13 03:01 Permalink RE: Activities not started against scheduled Use Filter with Percent complete is equal to zero which will give you activities not started in your update. Log in or register to post comments
Member for 19 years 3 months Member for 19 years 3 months Submitted by Giji Thomas on Tue, 2006-08-15 09:58 Permalink RE: Activities not started against scheduled Hi Steeven, This way it is correct, but some more If compaire VARIANCE TARGET-1 Es & EF with VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float) Filter is like: Level-1 VARIANCE TARGET-1 EARLY START - LT- 0 Level-2 Actual Dates -WR- Project Start date to data date (update) Level-3 %age Complete -WR - 1-99
Member for 22 years 11 months Member for 23 years Submitted by Steven Oliver on Tue, 2006-08-15 09:04 Permalink RE: Activities not started against scheduled Depends on the software you are using. P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful.
Member for 20 years 7 months Member for 20 years 7 months Submitted by Sunil Kumar on Sun, 2006-08-13 03:01 Permalink RE: Activities not started against scheduled Use Filter with Percent complete is equal to zero which will give you activities not started in your update.
Member for
19 years 3 monthsRE: Activities not started against scheduled
Hi Steeven,
This way it is correct, but some more
If compaire VARIANCE TARGET-1 Es & EF with
VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float)
Filter is like:
Level-1
VARIANCE TARGET-1 EARLY START - LT- 0
Level-2
Actual Dates -WR- Project Start date to data date (update)
Level-3
%age Complete -WR - 1-99
Member for
22 years 11 monthsRE: Activities not started against scheduled
Depends on the software you are using.
P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful.
Member for
20 years 7 monthsRE: Activities not started against scheduled
Use Filter with Percent complete is equal to zero which will give you activities not started in your update.