WBS calendar

Member for

20 years

Ok Kevin ... i’m sending it.



Thanks and regards.

Member for

22 years 3 months

I think it’s a good idea, send email to primavera with this enhancement request and they will put it on the list.



Cheers

Member for

20 years

Do u think it is possible for next release??

Member for

20 years

I understand and i’m agree.



But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.



Regards.

Member for

20 years

I understand and i’m agree.



But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.



Regards.

Member for

20 years 7 months

Yep that’s the case.



I don’t see how it could work any other way, because how would you treat grouped activities with multiple calendars? (not just by WBS, but also any other (combined) grouping)



H.T.H.

Member for

20 years

Niek,



I’m working with P3e ... is it still happening in P5??



Regards.

Member for

20 years

Thanks a lot Niek.

Member for

20 years 7 months

PRIM2849:



The original duration in the WBS summary bands is calculated as the following:



Latest Planned Finish - The Earliest Planned Start.



Project Manager uses the default Global calendar to determine the number of timeperiods based on the above calculation.



********************



This means that if your project calendar and the default global calendar are not the same, you can have deviations.



Hope this helps,



Niek.