Primavera Project Planner - P3 Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Tue, 2006-03-14 12:11 Permalink RE: Problems with different schedules Thanks Joao Ferreira ... think its going to help. Best Regards. Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Mon, 2006-03-13 19:15 Permalink RE: Problems with different schedules In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name. Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity). Cheers. Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Mon, 2006-03-13 13:59 Permalink RE: Problems with different schedules Thanks a lot ... but read again: "I created a different schedule for these resources, showing 9 hrs a day and 6 days a week, but even if the program asks me if I want to re-calculate the costs, it will always show 8 hrs a day for all resources." Regards Member for 21 years Member for 21 years Submitted by David Moses on Sat, 2006-03-11 06:41 Permalink RE: Problems with different schedules Dear friend, why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day. I hope this will help. Log in or register to post comments
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Tue, 2006-03-14 12:11 Permalink RE: Problems with different schedules Thanks Joao Ferreira ... think its going to help. Best Regards.
Member for 22 years 7 months Member for 22 years 7 months Submitted by Joao Ribeiro on Mon, 2006-03-13 19:15 Permalink RE: Problems with different schedules In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name. Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity). Cheers.
Member for 20 years Member for 20 years Submitted by Marcio Sampaio on Mon, 2006-03-13 13:59 Permalink RE: Problems with different schedules Thanks a lot ... but read again: "I created a different schedule for these resources, showing 9 hrs a day and 6 days a week, but even if the program asks me if I want to re-calculate the costs, it will always show 8 hrs a day for all resources." Regards
Member for 21 years Member for 21 years Submitted by David Moses on Sat, 2006-03-11 06:41 Permalink RE: Problems with different schedules Dear friend, why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day. I hope this will help.
Member for
20 yearsRE: Problems with different schedules
Thanks Joao Ferreira ... think its going to help.
Best Regards.
Member for
22 years 7 monthsRE: Problems with different schedules
In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name.
Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity).
Cheers.
Member for
20 yearsRE: Problems with different schedules
Thanks a lot ... but read again:
"I created a different schedule for these resources, showing 9 hrs a
day and 6 days a week, but even if the program asks me if I want to
re-calculate the costs, it will always show 8 hrs a day for all
resources."
Regards
Member for
21 yearsRE: Problems with different schedules
Dear friend,
why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day.
I hope this will help.