Problems with different schedules

Member for

22 years 7 months

In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name.

Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity).



Cheers.

Member for

20 years

Thanks a lot ... but read again:



"I created a different schedule for these resources, showing 9 hrs a

day and 6 days a week, but even if the program asks me if I want to

re-calculate the costs, it will always show 8 hrs a day for all

resources."



Regards

Member for

21 years

Dear friend,



why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day.



I hope this will help.