Baseline from another File or Excel
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Vasat, Chuck the data into Turbo-Chart (https://turbo-chart.com) and it'll allow you to see two scehdule datasets on one chart.
Hi Alexandre,
Thank you for your response.
As I came to find out, there doesn't seem to be a way to do it the way I described.
My work around was to save the baseline in TILOS and progress the activities based on the other.
Cheers,
Hi Vasat,
I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject
When you baseline a project, my experience is that you can only select activities in the current project.
Did you ask the question to Tilos people?
All the best,
Alexandre