Productivity Fields

Hello Vladimir,

Could you explain what are the following fields and how to use them:

Productivity [Current]

Productivity [Start]

Also there is the field Productivity [Actual] which is calculated based on actual hours and volume of work; however it is available only in performance archive, could it be extended into the Gantt Charts tables (Activity Gantt for example)? The value would be the weighed average of all periods of the resource assignments.

Best regards,

Bogdan

V
Vladimir Liberzon 👤 Member for 25 years 4 months

In Spider Project it is possible to set periods with different productivity of assigned resources.

Productivity [Start] shows initial productivity,

Productivity [Current] shows productivity at the data date.

These fields are calculated together with cost calculation.

Actual productivity is calculated for each assignment and it can be different for different activities of the same type.

The reasons for productivity deviations must be studied.

I would not recommend to use past productivity automatically for future activities scheduling.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts