Critical mass vs criticial path

The relationship between both subjects confuses me.

When I search the internet for the term "critical mass", specifically within turnarounds, I find almost nothing except the definition and that you should observe this so it does not become a problem for your turnaround.

As I understand it, critical mass items are in the beginning not on the critical path (have a lot of float), but due to the quantity of these items and your average work pace, they can become a problem when you do not closely follow them.

My questions:

  • is the term "critical mass" as important during a turnaround as the critical path ?
  • does software llike Primavera P6 or others automatically take the critical mass into account with some sort of report or trend lines ?
  • is there a best practice to cope with the critical mass concept during a turnaround ?
V
Vladimir Liberzon 👤 Member for 25 years 4 months

I don't agree. When there are few limited resources it is possible though hard to do it manually, if there are multiple limited resources in the complex program then only automatic resource levelling is practical. Project planner still have the control applying user defined activity priorities. If project model is correct then everything shall be right. We use resource levelling in most projects and do not loose control.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Vladimir

As I have said in previous disussions I do not like giving control of my programme to computer software to make my decisions.

I have used resource levelling on live programmes where the project only had two road scrapers and 200 hundred roads to repair so random allocation was not a problem - in fact it helped to stop arguments on priority from the area supervisors.

I can imagine the same result on a pipeline where only three automatic welding machines were deployed over 5 sections.

I have also used resource levelling on a disruption claim to show the likely result on completion if ONLY 40 were operatives deployed on a resource modelled programme.

But to try to level multiple resources over a complex 3d programme is to lose control.

Best regards

Mike Testro

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Mike,

basing on your comments: you are not satisfied with Asta resource levelling.

As well as any other software does not sound optimistic - you know that both MSP and P6 create awful resource constrained schedules. It is easy to be better than them as I expect Asta is. But still you are not satisfied. If this is true then I suggest you to try Spider. It is not right to spend a lot of your valuable time on unefficient manual resource levelling.

Regards,

Vladimir

 

S
Stephen Devaux 👤 Member for 21 years 2 months

Ah, but Mike, even if that is true, Asta still doesn't compute critical path drag.

Here is why this is relevant: critical path drag computation greatly assists the scheduler in compressing and optimizing the initial schedule. And that can allow a Spider Project user to resolve. without even realizing it, what would have been bottlenecks and lead to a shorter schedule.

For example, let us assume that a WIDGETER, needed for the one-week activity called WIDGETING, is available only during the first week of every month.

The Asta user does a little CPM schedule optimization limited to traditional CPM metrics and WIDGETING is scheduled for the second week in June. Then resource leveling is performed and WIDGETING slips to the first week in July, when the WIDGETER is available.

The Spider user does CPM schedule optimization which includes critical path drag and is thus easily able to compress the schedule so that WIDGETING is scheduled for two weeks earlier than with Asta, back to the last week in May. Now when resource leveling is performed, WIDGETING still slips to the next availability window -- only now that slippage is only to the first week in June, a month earlier than with Asta.

If WIDGETING is on the critical path, Spider Project's drag computation functionality may have saved a month of duartion and many hundreds of thousands of dollars (if not millions) because its resource leveling algorithm is operating on a drag-optimized schedule. And this is just one example -- how many situations like this are they in a 20,000 activity schedule?

I'm not at all meaning to give you a hard time, Mike. But Vladimir saw the value of drag computation and programmed it into Spider Project five years ago. Despite your nudging them, Asta has yet to act.

Fraternally in project management,

Steve the Bajan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Vladimir

Asta PowerProject will carry out resource levelling a well as any other software - Including Spider.

Best regards

Mike Testro

M
Mukesh Gupta 👤 Member for 12 years 1 month

Does any one has an idea/ referenece about what should be our WBS for decommissioning of mine ?

 

Regards

Mukesh Gupta

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Hi Floris,

Mike just never used the software that does resource leveling properly. It cannot be replaced by anything else.

Regards,

Vladimir

M
Mike Testro 👤 Member for 20 years 5 months

Hi Floris

My philosophy is NEVER EVER use resource levelling software.

Critical Mass as defined in the article seems to be planned resources deployed being larger than resources available.

This is displayed on most histograms as a red band over the available band.

Even P6 does it.

Why bother with expensive add ons?

Best regards

Mike Testro

F
Floris Gering 👤 Member for 11 years 10 months

Hi Mike

I thought that the defintion "critical mass" was a wellknown word in the scheduling theory after reading this article:

https://www.interplansystems.com/project-management-software/resource-leveling-critical-mass.html

They argument in the arcticle that resource levelling is often not the optimal approach for a turnaround schedule and they introduce the concept of critical mass. 

Has anyone thoughts, ideas or opinions about this article it's concepts ?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Floris

I think I am one of many on PP who have no idea what you are going on about.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts