Dears I need urgent answer,
1-In breif and steps how can i do impacted program on p6 ?
2- Should I updated whole activities or just only which I have to show their delay
Please help me quickly
Dears I need urgent answer,
1-In breif and steps how can i do impacted program on p6 ?
2- Should I updated whole activities or just only which I have to show their delay
Please help me quickly
Hi Amir Mina
Have you finalized the method you are going to asses the delays or to calculate the impact of delay event,only then detailing of procedure can be further discussed in this forum.
In you are using simplest method Impacted as planned , then you don't need to update the program
Cheer's
Shahul
Hi Amir
It doesnt matter waht software you use the principle is the same.
1. Create a list of delay events.
2. Establish the programme tasks that are affected.
3. Work out the actual impact date of the event.
4. Create a task that represents each event and link up using FS link.
5. Reschedule and note the delay effect - if any.
6. Go on to the next event.
Impacted Delay Analysis only works if the work is ongoing.
Therefore use the original contract programme before any progress.
The system is as good as your programme - constraints - SS FF Links - lead lags - will distort the results.
Best regards
Mike Testro