impacted program on p6

A
Amir Mina 👤 Member for 18 years 11 months

 

Dears I need urgent answer,

1-In breif and steps how can i do impacted program on p6 ?

2- Should I updated whole activities or just only which I have to show their delay

 

Please help me quickly

S
Shah. HB 👤 Member for 17 years 6 months

Hi Amir Mina

 

Have you finalized the method you are going to asses the delays or to calculate the impact of delay event,only then detailing of procedure can be further discussed in this forum.

 

In you are using simplest method Impacted as planned , then you don't need to update the program

Cheer's

Shahul

M
Mike Testro 👤 Member for 20 years 5 months

Hi Amir

It doesnt matter waht software you use the principle is the same.

1. Create a list of delay events.

2. Establish the programme tasks that are affected.

3. Work out the actual impact date of the event.

4. Create a task that represents each event and link up using FS link.

5. Reschedule and note the delay effect - if any.

6. Go on to the next event.

Impacted Delay Analysis only works if the work is ongoing.

Therefore use the original contract programme before any progress.

The system is as good as your programme - constraints - SS FF Links - lead lags - will distort the results.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts