Problems when importing from Excel to PrimaveraP6 V7

R
Rami Refaat 👤 Member for 14 years 9 months

Dear All

 

I am importing all the updates for my program from Excel files to the primavera, i am facing a great issue when importing dates, after i adjust all the dates and activities status and make sure that all of them have the same format which primavera accept i still get error, any suggestions, by the way i am using ASAP utilities and still have problems when importing dates.