scheduling based on resource availability

i would like to schedule activity based on the resource activity ex, ( i have 10 activities and i have 2 crew to execute the 10 activities  so what i want is the Primavera to schedule the activities that 2 activities in parallel then another 2.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

I think that creating resource "crew" you did not set its availability and P6 used default value 1/h.

If to set it as 2/h the results shall be as expected.

Regards,

Vladimir

A
Assem El-Tayibe 👤 Member for 16 years

Can u please tell me how to assign 2 crews as i have a labor resource call "crew" with default unit/ time = 1h/h and when i assign the resource and do the leveling it schedule;e the activities after each other , and what i want to have 2 activities in parallel.

 

regards,

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Assem,

this is the standard task for resource leveling.

If you will assign crews to activities, set the total number of available crews, and run resource leveling any project management software will delay those activities that require resources that are not available at the moment of their early start.

The main problem with leveling is selecting an optimal sequence of activity execution. With limited resources different packages may create different schedules for the same project.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts