Hi, I m new to p6 and encounter a question.
I m trying to do Foracast vs SoM. However, when I added the column, the list is empty. I check that they are I have some activities which are Start Milestones and Finish Milestones. However, for Milestones Date & SoM dates column, they are empty when I add the column.
May I know why? Can anyone assist me?
Thank you very much
IC. Thank You ver much.
Yifei,
You have to manually add data into User-defined fields yourself -They are not calculated by P6
Cheers,
G
Hi Gary,
SoM Date should reder to Schedule of Milestones Date which parked under user defined.
Hi Yifei,
Please could you tell me what "SoM" means?
Also, please could you tell me exactly which date column you are adding, that is blank (there are approx. 30 different date columns available in P6)