Can anyone tell me what is difference between mandatory start constraint and start on constraint?
What is its effect on early and late dates?
Hi everyone,
Can anyone tell me what is difference between mandatory start constraint and start on constraint?
What is its effect on early and late dates?
Vidhya,
Please see link to previous thread, where I explain the effects of all the constraint types in P6:
http://www.planningplanet.com/forums/planning-scheduling-programming-discussion/532479/differnce-between-mandatory-constraints-and
Cheers,
G