**URGENT** P6 6.2 Calandar Issues

J
John Sims 👤 Member for 15 years

Hi Everybody,

I have an urgent tender programme I must finish ASAP and my calandar won't calculate correctly.

My base calendar is set at 8hr/day 5 days a week, all my activities that use this calendar are fine (a day = a day)

But when i try to use a 7hr/day 5 days a week it does not calculate correctly, I have set this calendar with a 1 hour lunch break so it starts and finishes the same time as my 8hr day calendar.

If i add an activity using the 7hr/day calendar and put the duration as 1 day it starts at 9am but finishes at 10am the following day.

How do i get this to finish at 5pm the same day?

If you could help me that would be great.

 

John

R
Ronald Winter 👤 Member for 23 years 5 months

John,

The answer to your question depends upon what version of P6 you are using.  Gary gave you the answer for Versions before Version 7.  Version 7 and later can set the number of hours in a day in the calendar (if the Administrator’s setting allows this.)  Good luck!

G
Gary Whitehead 👤 Member for 17 years 2 months

John,

The reason for this is that in your admin>admin preferences>time periods options, you have 1 day set to equal 8 hours.

You could change this to 7 hours, but then you would just screw up all your activities that are on an 8hr/day caxlendar.

Better solution is to enter your durations in hours, rather than days. -e.g. for a 1 day duration on your 7h/day activities, type "7h" in the duration box.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts