Can anyone offer some advice, I have a client that has a different reporting period. Can you set up diiferent periods for different projects?
Can anyone offer some advice, I have a client that has a different reporting period. Can you set up diiferent periods for different projects?
You need to set up a seperate database.
Rgards
Paul E Harris
www.eh.com.au
Project Control Consultants and Planning and scheduling software book and training manual publishers