Cash flow could be created by primavera 6 version 7 using the reports section, However i found primavera 6 v7 reports are not very clear that every one can do it simply, Therefore see step by step how to create planned values and earned values using primavera p6 v7 reports.
create a schedule
add a resource from the resource directory (left hand side) you can call it lump sum in the details tab of the resource make sure that calcualte cost from units is NOT checked.
assign a resource to each activity
assign a cost to each activity via the resource
select view show on bottom select resouce usage profile
rigth hand side click resource usage profile options
on the data tab select costs
on the graph tab make sure that calculate average is not checked.
select print preview
click pagse setup
click the options tab and check the profile box and uncheck all of the other boxes.
there you have it
you can also assign a curve to the resource to distribute the cost the default uses a linear distribution.
Hi Hany
I tried to access, but they wanted to become a member before; so I don't know how you did it.
In the past I did the cash flow with P5 and P6. But due to the poor print quality of Primavera graphics I used Excel to print the graphics.
Hi Madan
you are wrong, it is possible, but there are other ways as well.
Regards to both of you
Dieter
Ex- I need to pay 20% on opening of my LC then after deliver rest 60% after receiving goods & testing, 6 months latter rest to be released. There is N. number of example where P6 will be failed to deliver. so don't follow this tutorial.